Last updated September 22, 2026 · updated every Friday and after key meetings live
The public records show delays and missed signals on both sides. The details, with sources, are on the full page.
Pick one. Each button opens an email, a web page or the share box; cards marked "Details coming soon" will switch on as soon as they're ready.
A community tracker built from about 140 City of Encinitas public records, the Encinitas Union School District's own statements, and the District attorney's letters. Demolition is done or underway. The permit for the actual rebuild is stuck on four connected disputes between the District and the City. This page lays out each one, what each side says, and what would unblock it.
Each step the rebuild must clear. Phase 2 cannot be approved until these disputes are settled (a Sept 8 hearing was targeted; its outcome is not public), and every approval carries roughly a month of appeal periods before work can start.
Scroll sideways to see the full path →
The single most useful thing to push for: a signed "at-risk" agreement letting the contractor start on the uncontested interior of the site while the traffic, land and easement questions are argued separately. The District requested it June 10; at the July 2 City Manager meeting the City said it was "open to an at-risk agreement once legal has reviewed and all parties sign off" (per the architect's notes). No signed agreement appears in the records.
Five terms do most of the work in this dispute. Everything below is the general meaning of the term, not either side’s position.
Ordered roughly from hardest to easiest to resolve. "City says" and "District says" are taken from the records; the "what unblocks it" line is this tracker's reading.
The records show delays on both sides. Keeping both in view is what makes this tracker credible to the people deciding.
Grouped by who has to act. Tick an item when it's done; it stays on the list, just marked. Click it again to untick. Ticks are saved only in your own browser.
Keep the ask neutral. The records show both sides contributed to the delay; a message that reads as anti-City or anti-District gets discounted by the body hearing it.
The traffic dispute is about how many cars can wait where. These are the lengths that appear in the records. Figures vary by source; where they conflict, the range is noted.
Read together: on-site loading more than doubles (180 → 400 ft, plus a new 180-ft K–1 facility), but because today's off-site zone on City right-of-way goes away, total west-side queue storage drops from 500 to 400 ft. The District's study finds the morning queue (about 19 cars, 380 ft) fits in 400 ft, but concedes 400 ft "would not likely be sufficient" at afternoon dismissal "if numerous parents arrive early and wait," and recommends attendants. The City's concern is the roughly 1,500 ft of street the pickup line uses today. The City has not shown an adopted source for requiring the queue to be "fully accommodated on-site"; the District's study does not address where 1,500 ft of waiting cars would go. That gap is the dispute.
Filter by who acted. Dark-red dots mark turning points.
Every unresolved item on the rebuild permit, who holds the ball, and where it stood when the records end.
| # | Item | City position | District position | Status | Ball with |
|---|---|---|---|---|---|
| 1 | Queuing | All queues on-site; no spillback onto Vulcan | No legal basis; wants a defined percentile/standard and existing-use trip credit | Open City redlines 9/4; District reply 9/9 | City |
| 2 | Left turn / U-turns | Southbound left "unworkable"; U-turns at Halcyon/Orpheus also rejected | Will drop the left turn; wants an integrated routing plan accepted | Open | Both |
| 3 | Vulcan dedication (10 ft) | Required (City written requirements also list the frontage improvements) | Does not concede City can compel it; conditional voluntary offer in Sept 4 letter | Open needs Council/legal resolution | City Council |
| 4 | Vulcan pavement | 19 ft from centerline ("roadway widening of 4'") | 15 ft authorized 7/28–30; City's 8/6 list still says District "not in agreement with providing any roadway widening" | Open 4-ft gap; no City reply after 7/30 | City |
| 5 | Union St | 8-ft dedication; public parking and pedestrian easements | Agreed to public parking and easements | Largely resolved 7/2; dedication status unclear | — |
| 6 | Old Vulcan easement | Vacation needs Council; team told to stop using the area | Wants it vacated; has raised eminent domain if the City refuses | Open vacation off critical path; fencing direction affects site logistics | City |
| 7 | Drainage / stormwater / hydromodification | 2024 BMP manual with infiltration; not exempt from hydromod | Redesigning after soil borings | Open resubmittal status after 7/30 unknown | District |
| 8 | Grading permit LDEV-040658 | 1st review 7/14; Leucadia Wastewater sign-off needed | — | Open | District |
| 9 | At-risk construction agreement | "Open to" it after legal review (7/2, DLR minutes); City says it allowed limited pre-permit grading, fencing, landscaping removal and playground demolition | Requested 6/10 | No signed agreement in records | Both |
| 10 | Phase 2 hearing + appeals | Zoning Administrator hearing, then 10-day City + 10-working-day Coastal appeal | — | Was targeted 9/8 no approval is public as of 9/21; if approved, appeals take roughly 4–5 weeks before work can start | City |
The records request went to the City only and effectively ends August 6. These are the gaps worth closing first.
Owner. Board of Trustees; Superintendent Andrée Grey; Asst. Superintendent Joseph Dougherty; Director of Facilities and Safety Eric Smith (public contact for site complaints). Counsel: Terry Tao, Tao Rossini APC.
DLR Group (architect; Daniel Moskop, Brian Leonard, Angela Bulkowski); Balfour Beatty (contractor); BDS Engineering (civil); Garland Associates (traffic); PlaceWorks (EIR).
Issues the coastal permits. City Manager Jennifer Campbell; City Attorney Ajit Thind; Development Services Director Scott Drapkin; Director of Engineering Dan Nutter; planner Christina Bustamante. Consultants: Tory R. Walker Engineering (stormwater), STC Traffic (traffic).
Division of the State Architect (DSA) approves the school buildings themselves; California Dept. of Education approved the plans Aug 19; the Coastal Commission hears appeals of City coastal permits.
The site is in the coastal zone, so a City permit is needed. Gov. Code 53094 lets the Board exempt the project from City zoning (done July 2026). Gov. Code 53097 still requires City drainage, grading and road rules for on-site work, but only "consideration" of off-site demands. Where that line falls is the fight.
Encinitas City Council (Item 12C traffic rules; easement vacation); City Zoning Administrator (Phase 2 permit hearing); EUSD Board of Trustees (schedule, costs, litigation).
How to read the sources: several key documents (the June 18 traffic minutes and the July 2 City Manager notes) were written by the District's architect and carry a "writer's impressions" disclaimer; the City never corrected them in the records, but they are one side's account. The July 27 board-workshop notes were written by a City staffer attending. Resident names from complaint letters are left off this page.